- Thursday, Jun 6, 2013The U.S. Department of Energy Office of Science (DOE-SC) assessed FRIB’s progress on June 4-5. The...
- Tuesday, Jun 4, 2013FRIB has successfully completed the annual ISO 14001 (Environmental) and OHSAS 18001 (Safety and...
- Wednesday, May 15, 2013FRIB has successfully completed the annual ISO 9001 surveillance audit of the Quality Management...
- Friday, May 10, 2013The high power beam dump is required to intercept all primary beam at powers of up to 325 kW. The...
- Thursday, Apr 11, 2013The baseline charge stripper is a flowing windowless film of liquid lithium approximately 10 µm...
- Monday, Dec 10, 2012Final design of FRIB technical systems is underway and progress in the Accelerator Systems Division...
- Thursday, Nov 15, 2012Steering high power ion beams cleanly through the FRIB driver linac and onto the rare isotope...
- Friday, Oct 26, 2012FRIB will need a production target different than what is presently used at NSCL. The beam power is...
- Wednesday, Oct 17, 2012Faculty members from Central Michigan University have joined into an academic partnership with...
- Monday, Oct 1, 2012Last week, the MSU Board of Trustees authorized construction of a new high bay for FRIB. The 27,000...
- Friday, Sep 28, 2012A team of MSU researchers has been awarded a grant to study how teams work together. The three-year...
- Friday, Sep 7, 2012The Michigan State University Board of Trustees has given its approval to the next step in the...
- Friday, Aug 24, 2012The Facility for Rare Isotope Beams at Michigan State University continues to progress with...
- Tuesday, Jul 31, 2012The second workshop on the collection of rare isotopes at FRIB, or Isotope Harvesting, was held on...
- Tuesday, Jun 26, 2012In its fourth decadal survey of nuclear physics, the National Research Council (NRC) outlines the...
- Friday, Jun 22, 2012The MSU Foundation Grants Committee recently awarded a Strategic Partnership Grant to a group of...
- Thursday, Jun 21, 2012The MSU Board of Trustees approved today the planning for a new 19,000 square foot high bay...
- Thursday, Jun 21, 2012The Detroit Free Press reported comments from U.S. Energy Secretary Steven Chu today in...
- Friday, May 18, 2012The ion source and low energy beam transport system used at Los Alamos National Laboratory in the...
- Friday, Apr 27, 2012The U.S. Department of Energy Office of Science (DOE-SC) Office of Project Assessment...
- Monday, Mar 19, 2012The Independent CD-2/3A Readiness and Cost Assessment Review, charged by MSU President Lou...
- Sunday, Mar 4, 2012One of the β=0.53 SRF cavities built by U.S. industry was shipped from MSU to Thomas Jefferson...
- Wednesday, Feb 22, 2012Successful ECR ion source tests conducted at Lawrence Berkeley National Laboratory (LBNL) produced...
- Monday, Feb 13, 2012Representatives from building trades organizations across Michigan met at FRIB on February...
- Wednesday, Feb 8, 2012For FRIB production, SRF cavities will be jacketed with titanium helium vessels. The fabrication...
- Monday, Jan 30, 2012The Michigan State University Board of Trustees has given its approval to the next step in the...
- Wednesday, Jan 25, 2012In the State of the Union Address last night, President Obama called for continued support...
- Tuesday, Jan 24, 2012Recycled steel shielding blocks (Duratek blocks) are being staged close to FRIB for just-in-time...
- Tuesday, Jan 17, 2012Multiple media reports speculated about funding for FRIB following a speech by Department of Energy...
- Friday, Jan 13, 2012The complete set of high temperature superconductor (HTS) coils have been assembled onto their...
- Wednesday, Jan 4, 2012Utility relocation work for FRIB is making good progress by moving the steam tunnels and other...
- Tuesday, Dec 27, 2011Located inside the superconducting radio frequency (SRF) cryomodules, cold beam position monitors (...
- Tuesday, Dec 20, 2011The Technology Demonstration Cryomodule (TDCM) has been assembled at FRIB, completing an important...
- Monday, Dec 19, 2011The Experimental Systems Advisory Committee (ESAC) met 14-16 December to evaluate progress and...
- Monday, Dec 12, 2011The FRIB Environmental, Safety and Health (ES&H) program was found ready to support a...
- Friday, Dec 2, 2011MSU is relocating utilities near the FRIB site to prepare for the start of civil construction in...
- Wednesday, Nov 30, 2011Membership of FRIB Users Organization (FRIBUO) jumped from 875 to more than 1,000 following votes...
- Tuesday, Nov 29, 2011U.S. Representative Tim Walberg from Michigan's 7th Congressional District toured FRIB and...
- Wednesday, Nov 23, 2011The Accelerator Systems Advisory Committee (ASAC) met November 15-17 to evaluate progress and...
- Wednesday, Oct 19, 2011The Superconducting Particle Accelerator Forum of the Americas (SPAFOA) held a meeting at FRIB on...
- Wednesday, Oct 5, 2011The U.S. Department of Energy Office of Science (DOE-SC) Office of Project Assessment conducted a...
- Thursday, Sep 15, 2011An article published at nature.com ("Isotope factory accelerates") covered the joint...
- Tuesday, Aug 23, 2011FRIB will be a new national user facility, enabling scientists to make discoveries. Potential users...
- Wednesday, Aug 17, 2011Staff members from eleven of Michigan's federal congressional offices were updated on the FRIB...
- Friday, Aug 12, 2011The superconducting radio frequency (SRF) design (i.e. the cold mass, which is primarily cavity,...
- Tuesday, Aug 9, 2011A peer review conducted last week of the fragment separator, mechanical design, target, beam dump,...
- Friday, Aug 5, 2011An FRIB Environmental, Health and Safety Advisory Committee (ESHAC) meeting and an external audit...
- Thursday, Jul 7, 2011A peer review conducted July 5-6 found the FRIB fragment separator optics design and diagnostic...
- Friday, Jun 24, 2011Several editorial articles have been published in newspapers around the state during the past week...
- Friday, Jun 17, 2011A peer review found the FRIB conventional facilities preliminary design on track for Critical...
- Tuesday, Jun 14, 2011In its Strategic Plan, the U.S. Department of Energy (DOE) defines its goal to “maintain a...
- Tuesday, Jun 7, 2011On Thursday, June 2, an ion beam was accelerated through the beta=0.041 cryomodules for the first...
- Thursday, Jun 2, 2011More work space - in the form another prefabricated trailer - was added as the Conventional...
- Tuesday, May 17, 2011MSU President Lou Anna K. Simon hosted and attended a meeting of the President's Project...
- Monday, May 2, 2011We are pleased to announce the selection of Donna M. Donovan, JD, to be the FRIB Deputy Project...
- Monday, Apr 18, 2011Beam commissioning of the ReA3 reaccelerator continued last week through the first cryomodule. On...
- Wednesday, Mar 30, 2011The U.S. Department of Energy (DOE) Office of Project Assessment and the Office of Nuclear Physics...
- Sunday, Mar 13, 2011Our thoughts and support go out to friends and collaborators in Japan following the recent...
- Tuesday, Mar 8, 2011The FRIB Science Advisory Committee (SAC) met on February 18-19 to consider the 16 FRIBUO...
- Wednesday, Feb 16, 2011The first accelerated beam through the ReA3 reaccelerator was identified today during...
- Monday, Feb 14, 2011The FRIB Project hosted two peer advisory committee reviews last week. The Experimental Systems...
- Friday, Feb 4, 2011Representatives from the FRIB Project met with experts from the University of Michigan, Fermi...
- Tuesday, Jan 25, 2011We welcome Thomas Borden to the FRIB Project as Experimental Systems Project Engineer. Tom...
- Wednesday, Jan 19, 2011The Detroit Free Press published a front page story about the progress and promise of FRIB. ...
- Friday, Jan 14, 2011Troy Hale, who splits his time between teaching in in Telecommunication, Information Studies &...
- Tuesday, Jan 11, 2011Brad Sherrill, FRIB Chief Scientist, was one of six Michigan State University researchers who...
- Monday, Dec 20, 2010Brookhaven National Laboratory reports good progress on their FRIB-funded research and development...
- Thursday, Dec 16, 2010The FRIB Quality Assurance (QA) group is performing training throughout the FRIB Project....
- Wednesday, Dec 8, 2010Barton Malow Company has been selected to serve as the Construction Manager-Agency (CM) for the...
- Friday, Nov 19, 2010Paul Chu will join the FRIB Project as a professor and lead the application software group in the...
- Thursday, Nov 11, 2010The Project Management Advisory Committee (PMAC) finished its review today at Michigan State...
- Tuesday, Nov 2, 2010We welcome Daniel Stout to the FRIB Project as FRIB Project Chief Engineer.Dan will provide...
- Friday, Oct 22, 2010Dr. Jie Wei joined the FRIB Project as Accelerator Systems Division Director in late August, and...
- Friday, Oct 15, 2010Matt Roush, author of the blog Great Lakes Innovation and Technology Report (GLITR), visited...
- Thursday, Oct 14, 2010Dr. William F. Brinkman, the Director of the DOE Office of Science, visited FRIB and MSU on October...
- Friday, Oct 8, 2010A workshop organized by Los Alamos National Laboratory (LANL) and MSU on “Isotope Harvesting...
- Monday, Sep 27, 2010Michigan lawmakers including Rep. Ed Clemente (D-Lincoln Park) and Sen. Gretchen Whitmer (D-East...
- Friday, Sep 24, 2010More than 70 members from the Capital Area Information Technology and Capital Area Manufacturing...
- Thursday, Sep 23, 2010A U.S. Department of Energy (DOE) environmental study of Michigan State University’s (MSU)...
- Wednesday, Sep 1, 2010Dr. Patricia M. Dehmer, DOE Office of Science (DOE-SC) Deputy Director for Science Programs,...
- Saturday, Aug 21, 2010BOSTON, MA -- A symposium entitled "Radiochemistry at the Facility for Rare Isotope Beams...
- Tuesday, Jun 29, 2010SmithGroup has been selected to serve as the architecture and engineering (AE) consultant for the...
- Friday, Jun 11, 2010EAST LANSING -- MSU President Lou Anna K. Simon charged an independent review panel to assess the...
- Thursday, Apr 22, 2010White House Office of Science and Technology Policy Assistant Director Kei Koizumi visited the...
- Wednesday, Mar 24, 2010The DOE NEPA hearing on the draft Environmental Assessment for FRIB at MSU was held last night.Vice...
- Friday, Mar 12, 2010A symposium "Radiochemistry at FRIB" will be held during the Fall 2010 National Meeting...
- Wednesday, Feb 24, 2010EAST LANSING, Mich. – During the conceptual design phase for the Facility for Rare Isotope...
- Wednesday, Feb 3, 2010The budget request that President Obama submitted to Congress includes $10 million for the...
- Thursday, Nov 12, 2009The Department of Energy (DOE) and Michigan State University hosted an educational open house and...
- Monday, Nov 2, 2009An educational open house and public scoping meeting are scheduled for Nov. 11, 2009.Michigan State...
- Monday, Nov 2, 2009Bradley Sherrill, FRIB Chief Scientist, was interviewed on Michael Feldman's Whad'Ya Know,...
- Monday, Jun 8, 2009EAST LANSING, Mich. — Michigan State University today announced the signing of a...
- Thursday, Dec 11, 2008EAST LANSING, Mich. — The U.S. Department of Energy Office of Science today named Michigan State...
- Thursday, Dec 11, 2008WASHINGTON, DC — The U.S. Department of Energy (DOE) announced today that Michigan State University...